Modular facade scaffold with advance guardrail

CETRAC MGS

The star of the show when it comes to leading guardrails – you can’t get any faster than this.

MGS replaces the traditional frame scaffolding: legs instead of a frame, with an advance guardrail on the inside and outside. Favourite: MGS-A with tilting lock quick-release fastener (patent pending), alongside the MGS-K with a tilting pin. Decking, brackets and accessories remain in use – only the frames, guardrails, diagonal braces and toe boards are replaced.

Available from2027
DIBt approval procedure not yet completed
380 Componentsin the online catalogue
DIBt approval procedure not yet completedexpected in the foreseeable future

Approval is expected in the foreseeable future – a plus for Germany; in most other countries it is not required. Until then in Germany: individual proof of stability – we will advise you.

MGS-A internal handle 2.00 m, CETRAC MGS (schematic diagram)
MGS-A internal handle 2.00 m
Adapter frame on frame scaffolding 70, CETRAC MGS (schematic diagram)
Adapter frame on frame scaffolding 70
Steel decking 0.74 m × 0.32 m, metric, CETRAC MGS (schematic diagram)
Steel decking 0.74 m × 0.32 m, metric

Schematic illustration based on catalogue dimensions; details may vary.

First-time customer MGS-A

Eisenberger Gerüstbau is switching to MGS-A

We were able to secure Eisenberger Gerüstbau GmbH as our first client: there, a total of at least 400,000 m² of facade scaffolding will be replaced with the MGS-A system.

Nico Labes, the managing director of Eisenberger Gerüstbau GmbH, was immediately impressed by the MGS-A quick-release fastener. In his view, it is the best system with a leading guardrail currently available on the market.
Exchange offer · MGS-A with front-mounted guardrail

Replace your frame scaffolding with the MGS-A version

You give us your frames, guardrails, diagonals and toe boards – and we supply MGS-A in return. You keep your own decks, brackets and other accessories and simply continue to use them with MGS-A.

First we sell your old material, then we deliver the new scaffolding – that is why it pays to start today ›

  • 1 frame→ 1 MGS standard
  • 1 Guardrail→ 1 MGS guardrails
  • 2 diagonal braces→ 1 new diagonal brace
  • 2 toe boards→ 1 new toe board
24 25 places available

First-time customer offer: For the first 25 customers to place an order, we’ll exchange 1 for 1 – you’ll only be charged for the additional parts.

What is MGS?

Poles instead of frames – the facade scaffolding with advance guardrail

In Germany and Europe, frame scaffolding has been used on building façades for decades, usually in widths of 0.70 or 1.00 metres. During assembly and dismantling, the scaffolder stands on a level that does not yet have any side protection.

The current health and safety regulations therefore require an advance guardrail: the guardrail for the next level must be installed from below before anyone steps onto it. With traditional frame scaffolding, this is only possible with additional components.

MGS is designed for this purpose. Instead of a frame, it has two uprights, with the guardrail running along the inside and outside. MGS therefore essentially replaces the frame scaffolding – providing the same façade work, but with side protection right from the start.

Facade scaffold and modular scaffold in one: MGS is used on facades like a frame scaffold, but is built in modular design – standards, ledgers and guardrails instead of frames.

Replace your frame scaffolding with the MGS version

You keep decks, brackets and accessories – we take frames, guardrails, diagonals and toe boards in part exchange: 1 frame for 1 MGS standard, guardrails 1:1, every two used diagonals or toe boards for one new part.

First-time customer offer: For the first 25 customers to place an order, we’ll only charge for the additional parts – 24 places still available.

How the exchange works ›

Two versions – one clear favourite

Our favourite

MGS-A with tilting lock

The star of the show when it comes to leading guardrails – you can’t get any faster than this.

Also available with metric guardrails: We also replace frame scaffolding from Plettac, Hünnebeck or Rux. A solution for every system ›

Place the guardrail over the tilting lock and let it drop down – that’s it. No fastening, no threading. When dismantling, the guardrail is simply lifted slightly from the standard that is still standing and removed – without operating the tilting lock. The metal, self-locking tilting lock (patent pending) saves assembly time for every bay, both during erection and dismantling. That’s hard cash for the scaffolder. Bay lengths 0.73 – 3.07 m or metric 0.74 – 4.00 m.

The tilting lock is made of stainless steel and painted red; the guardrail receiver – the bracket – is made of malleable cast iron, the same material as scaffold couplers. This is how we combine durability with the highest quality.

MGS-K with a tilt pin

Proven tilt-pin connection on the guardrail standard with the so-called “hook-on guardrails”: the guardrail is coupled to the upper tilt pin and fitted in advance with the next standard. Standard-size spigots – frame and modular scaffolds can be attached at any time. Slower than MGS-A when hooking in and out, and dismantling runs opposite to the direction of erection.

MGS-A or MGS-K – what counts in everyday use

MGS-A · tilting lockMGS-K · tilting pin
Lock on the standard Tilting lock: red-painted stainless-steel latch in a malleable-cast-iron bracket – lay the guardrail in from above, the lock secures itself. Every standard has two tilting locks and one perforated disc. Tilting pin: a pin on the guardrail standard to which the “Bärchen” guardrail is coupled – a different component from the tilting lock.
Tube connectors In standard dimensions – conventional frame and modular scaffolding can be attached and combined at any time. In standard dimensions – conventional frame and modular scaffolding can be attached and combined at any time.
Removing and installing guardrails Lift out any guardrail individually upwards at any time – without operating the tilting lock. The guardrails overlap in the direction of erection and are unhooked via the tilting pin at a specific angle – this takes longer.
Direction of erection and dismantling Free – erect and dismantle in any direction, and even open individual bays in between. Dismantling in the opposite direction to erection: the guardrail installed last must come out first – inherent to the system and cannot be solved otherwise.

Both MGS variants stay within the standard range. The difference is the lock: the tilting lock quick lock (patent pending) is the best lock in our range – faster to erect and dismantle and without a fixed sequence.

Your existing scaffolding will remain in use

Both options work with your existing materials: you can keep your decks, brackets and accessories. Only the frames, guardrails, diagonal braces and toe boards are replaced. For Plettac and Rux frame scaffolding, the standard pole is also available with a tilting lock – in which case you can continue to use your existing diagonal braces.

MGS-A in action

Hook it on? Let it drop – that’s it.

With the tilting lock quick-release fastener, the guardrail is simply placed over the tilting lock from above and allowed to drop into place. It locks securely in place straight away – no fastening, no threading, no tools required.

When dismantling, the fitter stands one level lower and cannot reach the upper tilting lock – nor does he need to: he lowers the first standard arm – the opposite movement to that used during assembly – and removes the guardrail by its tilting lock. At the other end, where the standard is still in place, he lifts the guardrail slightly and removes it – without operating the tilting lock. Of course, if you prefer, you can also remove the guardrail at any time by lifting the tilting lock.

This means that the advance guardrail moves along bay by bay in a single pass – both during assembly and dismantling. Every second saved per bay adds up to hours on the building site.

Video with no sound. The version shown is currently undergoing the approval process.

Explainer video with sound

Three solutions for advance guard rails compared

The video compares the three solutions on the market and shows how to switch your frame scaffolding to MGS-A.

Video with subtitles.

MGS-A in detail

Every MGS-A standard: two tilting locks, one perforated disc
Every MGS-A standard: two tilting locks, one perforated disc
Tilting lock, side
Tilting lock, side
Tilting lock, front view
Tilting lock, front view
Guardrail receiver (bracket) made of malleable cast iron
Guardrail receiver (bracket) made of malleable cast iron
Tilting lock – stainless steel, painted red
Tilting lock – stainless steel, painted red
Guardrail receiver (bracket), 3D view
Guardrail receiver (bracket), 3D view
Guardrail plate, steel 5 mm
Guardrail plate, steel 5 mm
Rosette 9.5 mm
Rosette 9.5 mm

Both variants: advance guardrail on the inside and outside, steel S460, hot-dip galvanised in our in-house galvanising plant (EN ISO 1461, DASt guideline 022).

MGS-A: tilting lock made of stainless steel, painted red – guardrail receiver (bracket) made of malleable cast iron, like scaffold couplers.

Technical data

Variants
MGS-A with tilting lock quick-release fastener · MGS-K with tilting pin
Closure
MGS-A: metal, self-locking tilting lock quick-release fastener (patent pending) · MGS-K: tilting pin
Standard
Ø 48.3 × 3.2 mm, S460, hot-dip galvanised – MGS-A: two tilting locks and one perforated disc per standard
Grid
Standard grid 0.73 – 3.07 m and metric 0.74 – 4.00 m – guardrails, decks and toe boards in both grids
Base point
Initial shaft 1.16 m with integrated starter section
Side protection
front-mounted, inside and outside – MGS-A with guardrails for the tilting lock quick-release fastener, MGS-K with ‘bear-shaped guardrails’
Galvanising
In-house galvanising plant, EN ISO 1461, DASt guideline 022
Items in the catalogue
511

Examples from the catalogue

ItemskgList price
MGS-A standard handle 1.16 m, integrated starter section, CETRAC MGS (schematic diagram)MGS-A standard handle 1.16 m, integrated starter section
MA-110-116
5,3861.55 €
MGS-A standard 2.00 m, CETRAC MGS (schematic diagram)MGS-A standard handle 2.00 m
MA 110 200
864.35 €
MGS-A internal handle 2.00 m, CETRAC MGS (schematic diagram)MGS-A internal shank 2.00 m
MA 112 200
864.35 €
MGS-A handrail post 1.00 m, CETRAC MGS (schematic diagram)MGS-A baluster 1.00 m
MA 114 100
4,2053.55 €
MGS-A standard support post for safety barrier 1.71 m, CETRAC MGS (schematic diagram)MGS-A support pole for protective screen 1.71 m
MA-115-171
769.85 €
MGS-A terrain support, upper end, CETRAC MGS (schematic diagram)MGS-A terrain support, upper end
MA-116-100
4,7046.15 €
0.24 m inlet section, CETRAC MGS (schematic diagram)Initial length 0.24 m
MA 128 024
1,4115.25 €
Extended inlet section 0.43 m, CETRAC MGS (schematic diagram)Extended starter section 0.43 m
MA-128-043
2,2039.35 €
Steel pipe coupler, CETRAC MGS (schematic diagram)Steel pipe coupler
MA-129-052
1,6013.35 €
Aluminium pipe connector, CETRAC MGS (schematic diagram)Aluminium pipe connector
MA-129-052A
0,8029.65 €
MGS-A guardrail 0.73 m, CETRAC MGS (schematic diagram)MGS-A guardrail 0.73 m
MA 210 073
1,4014.85 €
MGS-A guardrail 1.09 m, CETRAC MGS (schematic diagram)MGS-A guardrail 1.09 m
MA 210 109
215.35 €

List prices net. You can see your online price in the calculator and in the packages.

Packages with CETRAC MGS

New 77 m² · bay 2.57 m, 2 layersSample illustration

77 m² · bay 2.57 m, 2 layers

77 m² Bay 2.57 m Depth 0.73 m
available from 2027 · DIBt approval procedure not yet completed
51.39 €/m²
3,962.29 €net plus VAT
New 103 m² · bay 2.57 m, 3 layersSample illustration

103 m² · bay 2.57 m, 3 layers

103 m² Bay 2.57 m Depth 0.73 m
available from 2027 · DIBt approval procedure not yet completed
52.38 €/m²
5,384.71 €net plus VAT
New 108 m² · bay 2.57 m, 2 layersSample illustration

108 m² · bay 2.57 m, 2 layers

108 m² Bay 2.57 m Depth 0.73 m
available from 2027 · DIBt approval procedure not yet completed
49.07 €/m²
5,294.38 €net plus VAT
New 128 m² · bay 2.57 m, 4 layersSample illustration

128 m² · bay 2.57 m, 4 layers

129 m² Bay 2.57 m Depth 0.73 m
available from 2027 · DIBt approval procedure not yet completed
53.94 €/m²
6,931.77 €net plus VAT
New 139 m² · bay 2.57 m, 2 layersSample illustration

139 m² · bay 2.57 m, 2 layers

139 m² Bay 2.57 m Depth 0.73 m
available from 2027 · DIBt approval procedure not yet completed
46.96 €/m²
6,517.95 €net plus VAT
New 144 m² · bay 2.57 m, 3 layersSample illustration

144 m² · bay 2.57 m, 3 layers

144 m² Bay 2.57 m Depth 0.73 m
available from 2027 · DIBt approval procedure not yet completed
50.13 €/m²
7,213.90 €net plus VAT
New 180 m² · bay 2.57 m, 4 layersSample illustration

180 m² · bay 2.57 m, 4 layers

180 m² Bay 2.57 m Depth 0.73 m
available from 2027 · DIBt approval procedure not yet completed
51.74 €/m²
9,308.27 €net plus VAT
New 185 m² · bay 2.57 m, 3 layersSample illustration

185 m² · bay 2.57 m, 3 layers

185 m² Bay 2.57 m Depth 0.73 m
available from 2027 · DIBt approval procedure not yet completed
48.00 €/m²
8,880.31 €net plus VAT

Looking for scaffolding? We offer free, no-obligation advice – in German, English, French, Spanish, Russian, Ukrainian, Turkish and Hungarian.